2015-2016 Construction
 

We will post information regarding public meetings and plans on this website.  Our building has been renovated and added on to in several times over it's 70+ year history and we are excited to see this addition.

Southwest High School Construction Project Timeline

Southwest High School Construction Project

Timeline

  • August 24 – First day of school.  Four new classrooms open in former Media Center space.  New entry at door 5.

  • mid-September – Four new classrooms open in west addition space: 2 science labs, dance studio, music room. 

  • February/March 2016 – New kitchen and commons open.  Gradually move into new spaces, including new classrooms.  Asbesto Abatement Information

  • Spring/Summer 2016 – Renovate old cafeteria and kitchen area.    Install air conditioning throughout west building.  Asbesto Abatement Information

  •  August. 2016 – Entire project complete. 

Our Project managers are ATS&R from Minneapolis.

commons_1_jpg.jpg
PDF Draft Building plans   --  Clustering of departments. Draft plan. Not Final Plans.
Artist Renderings and Construction Images (when available)

Artist Renderings and Constuction Images